Date: Friday, August 16th 2019

Start Time: 10:00AM EST

End Time: 6:00PM EST

Expected Outage: 2 Hours

We will have two moments of downtime, once at approximately 10am EST, and another at approximately 6pm EST. This downtime is due to maintenance at the datacenter:

QuadraNet critical power vendors will be disconnecting critical load in order to perform the installation of a new MDP. At approximately 10:00AM EST, contractors will disconnect critical load on the MDP and install a temporary power source for customer's critical load, the downtime for this work will be approximately 15 minutes. There will be an 8 hour window where critical power vendors will be performing the installation of the MDP.

At approximately 6:00PM EST when the MDP installation has been completed, critical load will be disconnected and placed back on the permanent MDP, the downtime for the transition back to the MDP will be approximately 15 minutes



Tuesday, August 13, 2019





« Back